Operational Excellence & LEAN
From 45% to 85% Asset Intensity — A Full Operational Transformation of a Food Packaging Line
Sector:
Food & FMCG — Packaging and Production Operations
Scope:
TPM Implementation, SMED, DMAIC, Supply Chain Optimisation, Digital Transformation, People Development
The Challenge:
A food manufacturing packaging line was operating in a state of chronic underperformance. The numbers told a clear story — but the deeper problem was structural and cultural:
• Asset intensity of 45–50% — less than half the line's theoretical capacity was being used productively
• Unplanned stoppages above 35% — the line was stopping constantly, for reasons that were never fully understood or resolved
• Continuous runtime of no more than 4 minutes without at least one micro-stoppage — operators had accepted this as normal
• Packaging format changeovers were slow and unpredictable, limiting production runs to 8–10 hours of the same format before quality or stoppage issues forced a change
• A technical team overwhelmed by reactive firefighting, with no time or framework to address root causes
• No standardisation, no documented routines, no baseline to improve from
The line had the equipment and the people. What it lacked was structure, standards and a culture of ownership.
Our Approach:
We implemented a full LEAN programme structured around the 6 foundational steps — combining deep technical work with people development, supply chain collaboration and, ultimately, digital transformation.
Step 1 — Initial Clean and Identify The programme started with a major cleaning and inspection event across the entire line. Every machine, every component, every interface was examined. Hidden defects, chronic leaks, worn parts and unsafe conditions were documented and addressed. This was not just maintenance — it was the first act of the team taking ownership of their equipment.
Step 2 — CIL and Centrelining We implemented Cleaning, Inspection and Lubrication standards for every machine, with clear ownership assigned to operators. Centrelining defined the optimal settings for every format — eliminating the guesswork that had been causing variability and stoppages.
Step 3 — Key Standard Routines Detailed standard operating procedures were created for all critical machines and process steps. For the first time, the line had a documented baseline — and a reference point for identifying when things deviated from standard.
Step 4 — Supply Chain and Format Optimisation Working closely with the supply chain team and packaging material specialists, we conducted a full audit of packaging formats. The number of active formats was significantly reduced and the production sequence was restructured to minimise changeover complexity and time. SMED methodology was applied to every changeover — analysing, separating internal from external activities and systematically reducing format change time.
Step 5 — Root Cause Resolution With the standards in place, we turned to the chronic technical problems that had been accepted as inevitable. Detailed 5 Whys analyses were conducted on every major recurring stoppage. DMAIC projects addressed the systemic losses — each one resulting in a robust corrective action and a preventive maintenance plan that made the problem structurally impossible to recur.
Step 6 — People Development and Digital Transformation The final and most important step was transferring ownership to the team. Operators were trained to handle minor stoppages, lubrications and format changes independently — removing the dependency on the technical team for routine interventions. Technicians were freed to focus on complex problems and preventive work.
Once the team had the knowledge and the confidence, the line was digitised completely:
• All paper-based records were eliminated
• Maintenance logs, format change records, cleaning schedules and quality checks were moved to tablets
• Cameras were installed at the critical points of each machine — enabling real-time monitoring and remote diagnostics
• Workforce was restructured with a 40% reduction in headcount, made possible by the increase in team capability and the elimination of reactive firefighting roles
The Results:
BEFORE
Asset intensity — 45–50%
Unplanned stoppages — >35%
Continuous runtime without micro-stoppages — 4 minutes
Format changeover capability — Fixed 8–10h production runs
Workforce structure — High operational dependency and manual intervention
Documentation & data collection — Paper-based and incomplete
Team autonomy — Reactive teams dependent on technicians
----------------------------------------------------------------------------------------------
AFTER
Asset intensity — 80–85%
Unplanned stoppages — <5%
Continuous runtime without micro-stoppages — 480 minutes
Format changeover capability — Flexible and optimised production sequencing
Workforce structure — 40% operational efficiency improvement through autonomous operations
Documentation & data collection — Fully digital workflows using tablets and cameras
Team autonomy — Self-managing and proactive operational teams
----------------------------------------------------------------------------------------------
"The most powerful moment in this project was not when the numbers changed — it was when an operator stopped a line, identified the root cause, fixed it and restarted it, all without calling anyone. That is what operational excellence actually looks like."